Task
- Analysis of the recycling processes
- Introduction of preventive maintenance
- Reduction of downtimes
- Project manager “Increasing production capacity
Industry/ Function / Environment
- Recycling of aluminium slag
- Interim plant manager
- Optimisation of production processes
- Process analyses showed high proportion of non-value-added activities of employees, optimisation of task distribution
- Hiring of additional S&E staff, supporting production during late and night shifts
- Change of shift model led to extension of plant running times
- Preparation of S&E budget, build-up of spare parts stock for critical equipment, documentation of S&E measures in ERP system
- Preparation of investment “use of conveyor belts”, relief of internal transport, alternative use of logisticians
- Improvement of SCM: creation of additional production volumes
- Reduction of downtimes by 25%
- Introduction of 4-shift operation with existing personnel
- 4-shift operation enables production capacity to be increased by approx. 15%
- Norwegian subsidiary of an American group in the aluminium recycling industry with 2 locations in Norway
- 80 employees, 15 million € turnover